HMII3 Planning/PDR/Design/Construction
January 2020 - The contractor continued working on the restoration phase of the project by installing the first lift of asphalt as all underground construction is completed. The restoration progress is estimated to about 80% completed. The start up of the lift station has been rescheduled for the second week of January. Contractor and Engineer are working on sewer certification for the southeast quadrant of the project.
February 2020 - Reynolds has started the lamping inspection of the sewer mains. The lamping efforts will focus on the western third of the project area, then the middle third, and finally the eastern third. Package for Partial certification Number 1 which includes the southeast quadrant of the gravity sewer system has been submitted for review by the Engineer and then they would deliver the submital package to Broward County. Reynolds Construction to schedule a 48 hours dry test and the startup of the lift station. Installation of sewer mains is 100% completed
March 2020 - Lamping inspection for the sewer system was performed. Some defects were discovered during the inspection due to deflection in the pipe installation. Additional CCTV inspection was requested as City staff and the Engineer of Record have conducted live site review of the video to address the problem. AECOM recommendation is pending. Contractor has also submitted their letter requesting substantial completion. AECOM will also review and provide recommendation. Lift station has been certified. Certification for the southeast quadrant of the sewer system has also been received.
- January-2019
- February-2019
- March-2019
- April-2019
- May-2019
- June-2019
- August 2019
- September 2019
- October 2019
- November 2019
- December 2019
January 2019 - HMII3 Project Update
Wastewater –Reynolds Construction utilizing two sanitary sewer installation crews. One crew is installing gravity sewer mains along SW 20th Court, east of SW 67th Avenue toward SW 66th Avenue and the second crew is installing gravity sewer mains along SW 19th Street between SW 68th Avenue and SW 66th Avenue. NOTE – First lift of asphalt has been installed at the following locations: SW 68th Avenue from SW 25th Street to Pembroke Rd
February 2019 - HMII3 Project Update
02.25.19 Drainage Construction -Expect Road Closures and Detours Construction begins on SW 21st and SW 22nd Streets from SW 66th Avenue to SW 64th Avenue Construction on SW 67th Avenue from SW 23rd Street to SW 20th Street to SW 67th Lane is in progress. Roadway Restoration- Expect Road Closures and Detours Construction of curb, sub-grade and base begins on SW 18th Street and SW 20th Street between SW 66th Avenue and SW 68th Avenues Sodding swales begins along Sunshine Boulevard from SW 30th Street to SW 23rd Street Construction of sidewalks and curbs on SW 25th Street from SW 64th Avenue to SW 68th Avenue is in progress. Sanitary Sewer Construction Construction begins on SW 24th Street from SW 66th Avenue to SW 64th Avenue Construction on SW 67th Terrace to SW 66th Avenue is in progress 02.18.19 Drainage Construction-Expect Road closures and Detours SW 21st Street-between SW 66th Avenue and SW 64th Avenue begsin 2/18/19; SW 22th Street between SW 66th Avenue and SW 64th begins 2/18/19, SW 67th Avenue from SW 24th Street to SW 21st Street remains in progress. Sunshine Boulevard from SW 22nd Street to SW 20th Court remains in progress. SW 68th Terrace from SW 23rd Street to Sunshine Boulevard remains in progress.
02.09.19 Drainage Construction -Expect Road Closures and Detours SW19th Street- between SW 66th Avenue and SW 64th Avenue is in progress SW 20th Street between SW 66th Avenue and SW 64th Avenue remains in progress SW 67th Avenue from SW 24th Street to SW 21st Street remains in progress Sunshine Boulevard from SW 22nd Street to SW 20th Court remains in progress SW 68th Terrace from SW 23rd Street to Sunshine Boulevard remains is in progress Sewer Construction SW 66th Avenue between SW 25th Street SW 22nd Street sewer construction remains in progress. SW 67th Terrace between SW 20th Court to SW 66th Avenue sewer construction remains in progress. Drainage Construction SW19th Street- between SW 66th Avenue and SW 64th Avenue is in progress SW 20th Street between SW 66th Avenue and SW 64th Avenue remains in progress SW 67th Avenue from SW 24th Street to SW 21st Street remains in progress Sunshine Boulevard from SW 22nd Street to SW 20th Court remains in progress SW 68th Terrace from SW 23rd Street to Sunshine Boulevard remains is in progress. Roadway Restoration Sunshine Boulevard from SW 30th Street to SW 23rd Street extensive swale and irrigation restoration is in progress. Wastewater- Reynolds Construction continued running two crews on sewer. One crew continued laying sewer main along 20 CT, east of 67 Ave toward 66 Ave and the other has been laying sewer main along SW 67 toward 20 CT. Contractor has divided the installstion into three quardrants. Quardrant 1 includes the installation between Sunshine Blvd. and SW 68 Ave. Quardrant 2 includes all the streets between SW 68 Ave and SW 66 Ave. Quardrant 3 includes all the streets located east of 66 Ave. As of to this date, contrator has completed the installation of sewer main in quardrants 1 and 2 not including the installation of sewer laterals. Construction of sewer to date is at 48% complete.
If you have any questions please contact us at 954-998-3146 or hmii3@adamsconsulting.biz
March 2019 HMII3 Project Update
03.25.19
Roadway Restoration on SW 25th Street between SW 64th Avenue and SW 68th Avenue remains in progress No Parking in the Right-of-way or swales on the north or south side of SW 25th Street; Parking will only be permitted on the driveways, SW 25th Street going east from SW 68th Avenue to SW 66th Avenue curbs and sidewalks will be under construction. SW 25th Street going west from SW 64th Avenue to SW 66th Avenue roadway restoration will include subgrade and base course grading in preparation for the first lift of asphalt.
Roadway Restoration will begin on SW 20th Court at SW 68th Avenue going east. Please be prepared for delays and detours. Roadway Restoration on SW 20th Street from 68th Avenue to SW 66th Avenue remains in progress. Please be prepared for delays and detours.
Sewer construction begins on SW 66th Avenue from SW 20th Court to SW 19th Street. Please be prepared for delays and road closures. Sewer construction on SW 22nd Court and SW 22nd Street remains in progress. Please be prepared for delays and road closures.
Please expect delays and detours! Reynolds Construction will provide you with access in and out of your property. If you have any questions please contact us at 954-998-3146 or hmii3@adamsconsulting.biz
03.14.19
Reynolds Construction will be working on Saturday March 16, 2019 from 7am to 5pm to install “well points” along SW 66th Avenue going north beginning at SW 20th Court Segments of SW 66th Avenue beginning at SW 20th Court going north will be closed to traffic. Traffic will be detoured to SW 68th Avenue or SW 64th Avenue. Roadway detour signs will guide you. Please obey speed limits and acknowledge all roadway safety and detour signs.
03.06.19
Roadway Restoration- Curb Installation NO PARKING ON SW 25th Street Beginning Monday, March 8, 2019 at 7am through Friday Monday March 11, 2019 at 4pm there will be NO PARKING on the north side of SW 25th street between SW 66th Avenue and SW 64th Way. Beginning Monday, March 8, 2019 at 7am through Friday Monday March 11, 2019 at 4pm there will BE NO PARKING on the north or south side of SW 25th street between SW 64th Way and SW 64th Avenue Please make arrangement to park on a side street or on the opposite side of street Roadway Restoration- Curb Installation NO PARKING ON SW 18th Street Beginning Friday March 8, 2019 at 7 am through Monday March 11, 2019 at 4pm the curb will be installed on SW 18th Street between SW 67th Avenue and SW 66th Avenue No parking will be permitted on the south side of SW 18th Street Please make arrangements to park on a side street or on the opposite side of street
03.01.19
Wastewater- Reynolds construction continued running two crews on the sewer main installation. The contractor has now started the third phase of the project which moves all construction between SW 64 Ave and SW 66 Ave. Contractor has been installing sewer main simultaneously along SW 66 Ave toward north from Sw 25 Street and all side streets east of SW 66 Ave.
Restoration- The swales along Sunshine Blvd are being restored with the installation of sods. Curbs and valley gutters have been installed along SW 25th ST, SW 18 ST, SW 19 ST, and SW 20 ST. The ontractor has proposed to start construction along Pembroke Rd from SW 68 Ave to SW 64 Ave. starting on the first week of April 2019. All business owners along that road have been notified. Community meeting for all business owners was conducted on March 4, 2019 with only one attendee.
April 2019
Wastewater- Reynolds is simultaneously installing sewer main along SW 66 Avenue toward Pembroke Road and all the side streets east of that street, which considers the third phase of the installation. Percentage completion on the sewer installation to date is up to 65%.
May 2019 - Sewer installation is up to 78% complete. Contractor is currently working both day and night on he sewer installation as the permit for Pembroke allows installation to be conducted on two shifts
June 2019 - Storm Water. Storm water activities are progressing. Installation is up to 80% completed
September 2019 - • Physical Accomplishment to Date is listed as follow:
• Water Main Installation – 91%
• Installation of Gravity and Sewer Force main – 94%
• Installation of Drainage System – 82%
• Concrete Valley Gutter – 53%
• Pavement Restoration – 47%
• Lift Station Construction – 20%
• Complaints
• Total no. of complaints received to date – 348
• Total no. of complaints resolved to date – 216 (62% of complaints now resolved or closed)
• Total no. of complaints unresolved to date – 132 (38% are in the process of being resolved)
October 2019 - The work completed to date based on pipe installed include 99% water, 97% sewer, and 83% drainage. The contractor has increased the work force on restoration which estimated at about 53%. Complete overlay has been scheduled for the following roads: SW 23 ST, and SW 24 ST both from SW 64 Ave and 66 Ave, Pembroke Road from SW 68 Ave to SW 64 Ave. Revised proposal to replace the existing water Main on Sunshine Blvd is pending.
November 2019 - The sewer portion of the project is estimated at 100% completed based on the installation sewer mains. However the contractor continued making progress on restoration which includes curbs , sidewalks, and asphalt.
December 2019 - The wastewater construction based on pipes installation is estimated at 100 % complete. The lift station work is also completed. FPL was scheduled to energize the lift station this week.
October 2018 - HMII3 Project Update
Sewer Installation - Reynolds Construction continued working with two sewer crews. One of the crews continued installing sewer along SW 67th Terrace. The second crew continued working on adjusting sewer laterals to grade on location where the sewer main has already been installed. Sewer installation is completed on all the side streets west of SW 68th Avenue, including SW 68th Avenue from SW 25th Street to Pembroke Road. Sewer installation is also completed along SW 25th Street from SW 64th Avenue to SW 68th Avenue.
November 2018 - HMII3 Project Update
Sewer Installation - Reynolds Construction completed the sewer installation on all the side streets located west of SW 68th Avenue, including SW 68th Avenue from Pembroke Road to SW 25th Street. Sewer installation has also been completed along SW 25th Street from SW 64th Avenue to SW 68th Avenue. The Contractor also completed the installation of sewer main along SW 67th Terrace. Sewer installation is currently in progress along SW 67th Avenue, north of SW 67th Terrace.
December 2018 - HMII3 Project Update
Wastewater – The contractor is currently installing sewer main along SW 20 ST between SW 68 Avenue and SW 66 Avenue. Contractor has skipped the sewer installation along 67 Ave, north of SW 24 ST due to conflict with an existing 16” water main at that location. Construction associated with sewer is +/- 35% to date. Storm Water - The contractor is currently installing storm drainage at the following location: SW 20 ST, between (SW 68 Ave and SW 67 Ave), SW 25 ST, between (SW 68 Ave and SW 67 Ave). Drainage lamping inspection was conducted along SW 68 Ave as contractor is working to install the remaining segment of valley gutters between 21st ST and Pembroke Rd. Couple of structures still remaining to be installed in that area due to conflict with existing water main, which will be removed once the newly installed main is placed in service. Storm drainage Construction to date is +/- 36%. Water – The installation of water main has been temporarily suspended as contractor is currently conducting hydrostatic and disinfecting tests. Bac-tee testing has been conducted on finished pipeline(s) for certification purposes. The City and County have agreed to rebuild the existing interconnect between the two distribution systems with a bi-meter assembly with a by-pass. The connection will be located at SW 68th Avenue and SW 25th Street on the north side of SW 25th Street. The City and County will share the costs for the new assembly. The City and the County will develop a joint agreement for maintenance, calibration, billing, etc. Construction of water is +/- 55%. NOTE – First lift of asphalt has been installed at the following locations: SW 68th Avenue from SW 25th Street to SW 21st Street, SW 67th Lane from SW 67th Way to SW 20th Court SW 67th Way, SW 20th Street, SW 20th Court and SW 23rd Street, (all three streets west of SW 68th Avenue)