HMII3 Planning/PDR/Design/Construction

  1. January - 2020
  2. February - 2020
  3. March - 2020

January 2020 - The contractor continued working on the restoration phase of the project by installing the first lift of asphalt as all underground construction is completed. The restoration progress is estimated to about 80% completed. The start up of the lift station has been rescheduled for the second week of January. Contractor and Engineer are working on sewer certification for the southeast quadrant of the project. 

  1. January-2019 
  2. February-2019
  3. March-2019
  4. April-2019
  5. May-2019
  6. June-2019
  7. August 2019
  8. September 2019
  9. October 2019
  10. November 2019
  11. December 2019 

January 2019 - HMII3 Project Update                                                                                                                                                                          

Wastewater –Reynolds Construction utilizing two sanitary sewer installation crews. One crew is installing gravity sewer mains along SW 20th Court, east of SW 67th Avenue toward SW 66th Avenue and the second crew is installing gravity sewer mains along SW 19th Street between SW 68th Avenue and SW 66th Avenue.                                                                                                                                                                                                                           NOTE – First lift of asphalt has been installed at the following locations: SW 68th Avenue from SW 25th Street to Pembroke Rd


  1. October-2018
  2. November-2018
  3. December-2018

October 2018 - HMII3 Project Update                                                                                                                                                                                    

Sewer Installation - Reynolds Construction continued working with two sewer crews. One of the crews continued installing sewer along SW 67th Terrace. The second crew continued working on adjusting sewer laterals to grade on location where the sewer main has already been installed. Sewer installation is completed on all the side streets west of SW 68th Avenue, including SW 68th Avenue from SW 25th Street to Pembroke Road. Sewer installation is also completed along SW 25th Street from SW 64th Avenue to SW 68th Avenue.